Planned Activity Existing National Capacity

Major Outputs

Est. Budget (US $)

Refinement and expansion of the National General Survey

Limited 16 Enumerators

 

  • General Survey of all 14 accessible mine affected areas will be completed
  • 30 National staff will be trained in Impact Survey, Planning and MIS
50,000
Technical Survey of high impacted areas. Expansion by 1 team.

Limited 8 Surveyors

  • Expansion by at least one survey team (6 additional Surveyors)
  • Technical Survey of 1,800,000 m2
215,560
Expansion of the National Manual Demining Capacity by 1 team

Limited 19 Deminers

  • 63 National staff will be trained in Demining Skills
  • 800,000 m2 of mine/UXO contaminated areas would be cleared.
1,113,230
Mine Detecting Dog Support
Capacity building
No National Capacity in place
  • 18 dogs and National dog handlers will be trained
  • 2 dog trainers would be trained
  • 750,000 m2 area will be cleared
1,675,600
National EOD Capacity Building No National Capacity in place
  • 10 National EOD staff will be trained and equipped to form 2 teams
  • 500 EOD clearance tasks would be performed
142,640
National Mine Action Training and Monitoring Capacity Building No National Capacity in place
  • 5 Demining instructors would be trained
  • 15 monitoring missions
  • 10 revision training courses would be constructed
85,180
Feasibility Study of Mechanical Support to Mine Action No National Capacity in place
  • Mechanical Mine Clearance Feasibility study designed and conducted
  • Suitable equipment would be identified
  • Detailed report of the study prepared
19,100
Socio-Economic Impact Survey and National Mine Action Planning

Limited 16 Enumerators with basic skills

  • 30 National Staff would be trained in Impact Survey Procedures
  • 10 National Staff woud be trained in data management and use of data
  • All suspected communities would be surveyed
  • A realistic national strategic plan would be devised
800,000
Management Information System Improvement

Limited 3 National Staff

  • 4 Local Staff will be trained in Mine Action data management tools
  • Necessary equipment would be procured and installed
Covered under Resource and Mobilization and Capacity Building
Quality Assurance Capacity Building No National Capacity in place
  • National QA standards will be established
  • 4 local QA officers will be trained
  • QA of all cleared tasks would be performed
  • Safety of clearance ops. will improve
Covered under National Mine Action Training and Monitoring Capacity Building
Mine Awareness Education

Limited 15 Master Trainers

  • MA training for 800 health workers and 500 teachers
  • Stage show in 18 districts
  • Publication of MA material
  • Monitoring/Evaluation of all MA activities

240,000

Management Capacity Building

Limited HQ and a regular office with basic skills

  • 6 Senior mangers and
  • 10 mid-level managers will receive Management/Planning training
  • Safety, productivity and cost effectiveness of mine action would improve
Covered Under Resource Mobilization and Capacity Building
Resource Mobilization and Capacity Building Not Exisiting
  • 4 national staff will be trained in proposal, grant and report writing
  • ANAMA senior staff will be trained and involved in donor relations
453,300
United Nations Technical Support Technical Advisors
  • Assist ANAMA with technical, planning and management skills
437,340

Back to Article

 

 
 